East Broadway Avenue Road Rehabilitation between Glade Street and 5th Street, Muskegon Heights, MI

Phase Three Construction Start: March 2026 Phase Three Construction End: July 2026

PROJECT PROFILE

Broadway Avenue
  • 3,000 ft of road reconstruction
  • 1,000 ft of 12-inch storm sewer
  • 4,100 ft. of 4-inch to 16-inch water main
  • 26 lead water service line replacements
  • Miscellaneous Sanitary Sewer improvements

 

What Is Being Done?

  • Asphalt Removal and Replacement
  • Sidewalk and Curb Removal & Replacement
  • Drainage Structure Adjustments
  • Restoration
  • Replacement of Water Mains
  • Lead Service Line Replacement

How Will Traffic Be Impacted:

For convenience and to cause minimum disruption to the residents of Muskegon Heights, the project has been
constructed in three phases. This is the final phase of the project.

  • Broadway Avenue will be closed to thru traffic at Glade Street and at 5th Street
  • Broadway Avenue access will be closed off to all side streets except Temple Street and 6th Street
  • The posted detour for Broadway will run along Glade Street to Summit Avenue to Peck Street to Broadway
  • During construction, when driveways are inaccessible, we encourage residents to park on side streets.
  • Traffic to businesses and residents will be maintained utilizing side streets and alleys.
  • Pedestrian traffic will be detoured as necessary.

Contractor: McCormick Sand
24-hour Emergency Contact: Rob Murphy, 231-740-8894
City of Muskegon Heights Contact:
Khi Guy, Public Works Director, 231-332-6762
Josh Allen, Utilities Director, 231-955-0050